Page 62-63 - Handbook on Vital Statistics

Basic HTML Version

[47]
KPI
Target 2013
Actual Achievement
Score
Weightage
3.2 Percentage reduction of accidents in 2014
for rehabilitated blackspots in 2011
60%
Target increased
from 50%
84.07%
Federal Roads : 93.81%
reduction
Highways : 70.55% reduction
140%
3.3 Number of locations provided with
signalized pedestrian crossing for schools
35
locations
35
Physical works completed at 35
locations
100%
3.4 Percentage reduction of accidents in 2014
for schools with pedestrian crossing built in 2011
70%
Target increased
from 50%
94.21%
(Before : 207, After : 12)
135%
3.5 Number of roads upgraded & maintained to
strategic & economic locations
15
locations
15
Completion of15 pedestrian
crossings
100%
3.6 Completion of upgrading works of 15 bridges
in critical condition
9.33%
(Cumulative: 85%)
13.99%
89.66% of upgrading progress
9 bridges completed
150%
3.7 Number of projects completed for the
rehabilitation and upgrading works of the Pan
Borneo Road
30
projects
30
30 projects completed
100%
4. Improving the quality of Highways network
4.1 Progress of construction of Seri Kembangan
Interchange to improve traffic dispersal
50%
(Cumulative: 50% of
61.48
61.48% of physical progress
123%