Dimensi
Prestasi
Petunjuk Prestasi Utama
Sasaran 2015
Pencapaian
Sebenar Sehingga
30.09.2015
Peratus
Pencapaian
(
capped at 100%)
schools with pedestrian crossing built
in 2012
Number of locations upgraded &
maintained its road connectivity to
strategic & economic locations
20 locations
20 locations
completed
100%
Percentage completion of upgrading
works of 15 bridges in critical condition
100%
100% / 15 bridges
completed
100%
Number of projects completed for the
rehabilitation and upgrading works of
Pan Borneo
14 projects
14 projects
completed
100%
Maklumat pencapaian disediakan oleh Urus Setia KPI Kementerian Kerja Raya
Kecekapan dan
Keberkesanan
Penyampaian
Perkhidmatan
Awam
Percentage of repainting of Road
Markings using thermoplastic materials
30%
32.45%
100%
Percentage construction of Seri
Kembangan Interchange
100%
100%
100%
Increasing Quality of Workers:
1. Number of construction personnel's
competency level evaluated through
training and assessment (40,000)
2. Rate of absorption of trained
construction personnel and youth by
100%
128.6%
100%